Timeline of the Build

Below is a schedule of works to be carried out at Thirsk Lodge Barns over the coming months.

Obviously the Great British weather may impact some of the timings but this is the plan!

AUGUST

  • Strip back roof of Mezzanine Area and VIP Room

  • Continued work on exterior brick work (pointing)

  • Construction of pillars in dining room

  • Prepare roof trusses

  • Lantern ordered

  • Final flooring ordered and internal specs. in final discussions

  • Rafters arrive for rest of the roof trusses, including the entrance area to join the two sets of Barns

SEPTEMBER

  • Roof structure on Main Barn goes up ready for tiling

  • Roof structure on Dining Room goes up ready for tiling

  • Lantern arrives

  • Final Ground Source Heating plans drawn up

  • Glass (Windows and doors) being measured

OCTOBER

  • Electricians start on site

  • Plumbers start on site

  • Slabs go down for entrance; joining the two sets of Barns

  • Ground Source Heating installed

  • Landscaping in paddock starts

NOVEMBER - JANUARY 

  • Windows and doors fitted

  • Landscaping around car park starts

  • Car park installed

  • Aim is to be water tight by December!

FEBRUARY - MAY

  • Finishing touches; flooring down, bathrooms in, bar installed, lighting fitted etc.

JUNE / JULY – Open!