Timeline of the Build
Below is a schedule of works to be carried out at Thirsk Lodge Barns over the coming months.
Obviously the Great British weather may impact some of the timings but this is the plan!
AUGUST
Strip back roof of Mezzanine Area and VIP Room
Continued work on exterior brick work (pointing)
Construction of pillars in dining room
Prepare roof trusses
Lantern ordered
Final flooring ordered and internal specs. in final discussions
Rafters arrive for rest of the roof trusses, including the entrance area to join the two sets of Barns
SEPTEMBER
Roof structure on Main Barn goes up ready for tiling
Roof structure on Dining Room goes up ready for tiling
Lantern arrives
Final Ground Source Heating plans drawn up
Glass (Windows and doors) being measured
OCTOBER
Electricians start on site
Plumbers start on site
Slabs go down for entrance; joining the two sets of Barns
Ground Source Heating installed
Landscaping in paddock starts
NOVEMBER - JANUARY
Windows and doors fitted
Landscaping around car park starts
Car park installed
Aim is to be water tight by December!
FEBRUARY - MAY
Finishing touches; flooring down, bathrooms in, bar installed, lighting fitted etc.
JUNE / JULY β Open!